What is a Material Indent Form?
A Material Indent Form (also called Site Material Requisition / SMR or Indent Slip) is the document a site supervisor or engineer raises to request material delivery from the central store, head office or vendor. It's the gateway between the site team and the procurement / store team. Without it, materials show up either too early (cluttering the site, getting damaged), too late (work stops, mazdoors sit idle on full wages) or wrong-grade (cement of a different brand, steel of a different diameter).
On Indian sites, indents are usually paper-based — handwritten, signed, photographed and WhatsApped to the store keeper or owner. This template gives you a clean, professional PDF you can print as a pad and use site-wide.
When is it used?
Whenever site needs material that isn't already on stock — daily for fast-moving items like cement, steel and aggregate; weekly for finishing materials; one-off for specialty items like waterproofing chemicals or specific tile lots. Indents are filed and used to verify delivery challans (DC) when materials arrive.
Key fields in this indent form
- 1. Indent number (sequential per site)
- 2. Date raised + project / site name
- 3. Indented by (supervisor / engineer name + signature)
- 4. Material code, description, brand / specification
- 5. Unit (bags / nos / kg / cum) and quantity required
- 6. Available stock at site
- 7. Required-by date
- 8. Urgency (Normal / Urgent / Emergency)
- 9. Purpose / activity / location it's needed for
- 10. Approver name + sign-off (PM / project head)
- 11. PO number (filled by procurement)
- 12. Delivery confirmation / DC number (filled when received)
How to fill — step by step
- Check current site stock first. Don't indent what you already have.
- Specify the item completely — brand, grade, size. "Cement OPC 53 grade Ultratech 50kg bags" not just "cement".
- Compute quantity from work plan — 7-day need + 20% buffer.
- Mark required-by date — give procurement at least 48 hours unless emergency.
- Get supervisor's signature on site, then send to PM for approval.
- Match the DC to the indent when material arrives — file together.
Common mistakes
- Vague specs. "Steel" gets you 8mm when you needed 16mm. Always specify diameter, grade, length.
- No approver sign. Without sign-off, vendors deliver and PMs deny. Always get the approval column filled.
- Indenting too late. "Need cement tomorrow" means premium prices and delays. Plan 3 days ahead.
- Not closing the loop. Match indent to DC. Without that, theft and shortages can't be tracked.
- Same indent, multiple times. Sequential numbering prevents duplicate orders.
How Site Setu automates this
Site Setu's Material module digitises the indent → approval → PO → delivery → consumption loop. Supervisor raises an indent on mobile, PM approves with one tap, procurement converts to PO, vendor delivers, store-keeper scans DC, system reconciles. No paper, no missed deliveries, no theft. Features · Pricing.
Stop Filling Indents Manually
Site Setu digitises indent → approval → PO → delivery — all in real time, with stock and consumption auto-tracked.